Brampton Watermain & Sewer Replacement

T2 Utility Engineers (T2ue) completed a Subsurface Utility Engineering (SUE) investigation for Ivan B. Wallace (IBW). IBW was hired by CH2M Hill (Region’s Engineer) for the Region of Peels’ watermain and sewer replacement (and rehabilitation) project in downtown Brampton.

The field investigation was completed between July and September 2016. The SUE investigation for this project provided key information regarding the location of the existing underground utilities to be used during the design and construction of the project. A combination of data from the field investigations and utility record information was used to create the composite utility drawings (as per CI/ASCE Standard 38-02).